SABA TOWER

— is a new modern Class A business center, that adheres to international standards and is located in the business center of Almaty city
Satpayev St. 29g

5
FLOORS
275
NUMBER OF PARKING SPACES
38 950
М2 TOTAL AREA



INFRASTRUCTURE

SABA TOWER provides easy access to key points of the city



SEISMIC RESISTANCE

Steel structures are traditionally considered a reliable solution for construction in areas with high earthquake resistance due to the high strength and ductility of the structural material, high manufacturing quality, as well as the reliability of the mounting joints.

SABA TOWER to withstand earthquakes measuring up to 10 on the Richter scale.


CONSTRUCTION PROGRESS

The facility has been commissioned

  1. Terrace screed installation works are in progress.
  2. Completed work stages are being submitted for technical supervision inspection.
  1. Final works on balcony cladding are in progress.
  2. Preparatory works for screed installation on the terrace have commenced.
  3. Final works on the installation of internal piping systems are in progress.
  4. Installation works of ventilation ducts are nearing completion.

1. Handover works for the ventilated facade are in progress.
2. Handover works for the terrace waterproofing are in progress.
3. Piping layout works inside the building are nearing completion.
4. Installation works of ventilation ducts are ongoing.

1.    Installation works for the entrance group have been completed.
2.    Handover works for the ventilated facade are in progress.
3.    Handover works for the terrace waterproofing are in progress.
4.    Internal pipeline installation works are nearing completion.
5.    Installation works for ventilation ducts are ongoing.

1.    Installation of the entrance group is nearing completion.
2.    Handover works for the ventilated façade are in progress.
3.    Installation of internal piping within the building is nearing completion.
4.    Installation of ventilation ducts has begun.

1.    Installation works for the entrance group are nearing completion.
2.    Installation of the ventilated facade and parapet cladding works are ongoing.
3.    Pipeline installation works inside the building are in progress.
4.    Ground preparation works for site landscaping are ongoing.

1.    Roofing works on the 6th floor have been completed.
2.    Installation of the entrance group is ongoing.
3.    Installation of the ventilated façade and parapet cladding is ongoing.
4.    Internal pipeline routing works are in progress.
5.    Preparatory works for ground planning for site landscaping have been started.

1.    Roofing works on the 6th floor have been completed.
2.    Installation of the entrance group is in progress.
3.    Installation of the ventilated façade and parapet cladding works are ongoing.
4.    Installation and routing of pipelines inside the building are in progress.

1.    Roofing works on the 6th floor are nearing completion.
2.    Preparatory works for the installation of the entrance group are underway.
3.    Installation of the ventilated façade and parapet cladding works are ongoing.
4.    Internal pipeline distribution works are in progress.

1.    Elevator commissioning works have been completed.
2.    Roofing works on the 6th floor are in progress.
3.    Installation of the ventilated facade is ongoing.
4.    Internal pipeline installation works inside the building are ongoing.

1.    Elevator commissioning works are ongoing.
2.    Construction works for the terrace on the 5th floor have been completed.
3.    Roofing works on the 6th floor are in progress.
4.    Assembly of the 0.4 kV switchgear with connection to the transformer substation is ongoing.
5.    Installation works of the ventilated façade are ongoing.
6.    Monolithic works on the retaining wall on the eastern side have been completed.
7.    Installation of internal pipeline systems within the building is ongoing.

1.    Elevator commissioning works have been initiated.
2.    Works on the construction of the 5th-floor terrace are in progress.
3.    Roofing works on the 6th floor have been initiated.
4.    Assembly of the 0.4 kV switchgear with connection to the transformer substation is in progress.
5.    Installation works of the ventilated façade are ongoing.
6.    Monolithic works on the retaining wall on the eastern side have been initiated.
7.    Internal pipeline installation works inside the building are ongoing.

1. Elevator assembly works are ongoing.
2. Construction works for the 5th-floor terrace are in progress.
3. TP and 0.4 kV switchgear: assembly of the 0.4 kV switchgear with connection to the TP is ongoing.
4. Installation of the ventilated façade is ongoing.
5. Works on the retaining wall on the western side have been completed.
6. Preparatory works for the retaining wall on the eastern side are in progress.
7. Ventilation equipment has been procured.

1.    Works on the installation of fire compartments and stained-glass glazing are nearing completion.
2.    Elevator assembly works are ongoing.
3.    Construction works on the 5th-floor terrace are in progress.
4.    Installation of equipment for the pumping stations and the BTP has been completed.
5.    Transformer substation (TS) and 0.4 kV switchgear. Assembly of the 0.4 kV switchgear with connection to the TS is ongoing.
6.    Installation works of the ventilated façade are ongoing.
7.    Backfilling works near the southern retaining wall have been completed.
8.    Preparatory works on the western retaining wall are in progress.

1.    Works on installing fire barriers and glazing the curtain walls are underway.
2.    Elevator assembly works are ongoing.
3.    Terrace construction on the 5th floor is in progress.
4.    Installation of equipment continues:
•    Pump stations – domestic drinking water, fire-fighting, and APT. Installation of electrical cables to the main switchboard;
•    Assembly of the BTP has been completed. Installation of electrical cables to the main switchboard;
•    TP and RU-0.4 kW. Assembly of RU-0.4 kW with connection to the TP is ongoing.
5.    Installation of the ventilated façade continues.
6.    Backfilling works near the southern retaining wall are underway.
7.    Construction of retaining walls continues.

1.    Works on installing fire barriers and glazing the façade with stained-glass units are underway.
2.    Elevator installation and assembly works are ongoing.
3.    Construction of the terrace on the 5th floor is in progress.
4.    Installation of equipment continues:
•    Pump stations for domestic water supply, fire extinguishing and APS (Automatic Fire Suppression). Pumps have been installed, pipeline connection works are in progress;
•    Assembly of the BTP (block transformer substation) has been completed;
•    TP and 0.4 kW switchgear: transformers have been installed, raised floor installation is ongoing.
5.    Installation of the ventilated façade is ongoing.
6.    Landscaping works are in progress.
7.    Construction of retaining walls continues.

  1. Installation of fire barriers and glazing of curtain walls is in progress.
  2. Elevator installation works are ongoing.
  3. Construction of the terrace on the 5th floor is underway.
  4. Ventilated façade installation is ongoing.
  5. Landscaping works on the east side of the building are in progress.
  6. Preparatory works for the retaining walls have started.
  7. Installation of engineering equipment continues:
  • Pumping stations (domestic water supply, firefighting, and automatic fire suppression): pumps have been installed, piping connections are in progress;
  • BTP (Boiler Transfer Point): large modular blocks have been delivered, assembly is in progress;
  • TP and LV switchgear (0.4 kV): transformers have been installed, raised floor installation is underway.

    1. Installation of fire barriers and glazing of stained-glass windows is in progress.
    2. Elevator assembly works are ongoing.
    3. Assembly of the fire-fighting water tank is being completed.
    4. Roofing works on the 6th floor and terrace works on the 5th floor are in progress.
    5. Preparatory works for equipment installation have started, including:
    • pumping stations for domestic water supply, fire-fighting, and APT systems;
    • BTP;
    • TP and switchgear 0.4 kV.
    6. Installation of the ventilated façade is ongoing.
    7. Preparatory landscaping works have begun on the eastern side.

  1. Installation of fire barriers and glazing of stained-glass windows is in progress.
  2. Elevator assembly works are ongoing.
  3. Installation of the fire-fighting water tank is underway.
  4. Roofing works on the 6th floor and terrace works on the 5th floor are ongoing.
  5. Fire pump station and APT equipment have been purchased.
  6. Installation of the ventilated façade has started.
  1. Masonry works for partitions on the 6th floor are being completed.
  2. Installation of fire barriers and glazing of curtain walls is in progress.
  3. Elevator installation works are ongoing.
  4. Installation of the fire escape steel structures has been completed. Assembly of the fire-fighting water tank is in progress.
  5. Roofing works on the 6th floor and terrace works on the 5th floor are in progress.
  6. Preparatory works for the installation of power transformers, 10 kV and 0.4 kV switchgears are ongoing.
  7. Equipment for the modular heating unit has been purchased.
  8. Preparatory works for the installation of the ventilated façade have started.
     
  1. Masonry works for the 6th floor partitions are ongoing.
  2. Installation of fire barriers and glazing of stained-glass windows is in progress.
  3. Elevator assembly works are ongoing.
  4. Installation of metal structures for the equipment platform has been completed. Installation of metal structures for the fire escape is in progress. Assembly of the fire-fighting water tank has started.
  5. Preparatory works for the roofing of the 6th floor are ongoing.
  6. Preparatory works for the installation of power transformers, 10 kV switchgear and 0.4 kV switchgear are ongoing.
     
  1. Masonry works for internal partitions up to the 5th floor have been completed. Masonry works for the partitions on the 6th floor are in progress.
  2. Installation of facade glazing structures up to the 5th floor on the east and south sides has been completed. Installation of facade glazing structures on the north side is ongoing. Works are underway for installing fire barriers and glazing with stained glass panels.
  3. Elevator assembly works are ongoing.
  4. Installation of metal structures for the equipment platform is ongoing. Installation of metal structures for the fire escape has begun.
  5. Preparatory works for the installation of the 6th floor roof are in progress.
  6. Equipment for the domestic water supply pumping station has been purchased.
  7. Preparatory works for the installation of power transformers, 10 kV switchgear, and 0.4 kV switchgear are in progress.
     
  • Masonry work on internal partitions up to the 5th floor is nearing completion.
  • Partition masonry on the 6th floor has commenced.
  • Installation of façade glazing systems on the 5th floor is nearing completion.
  • Fire barrier installation is in progress.
  • Glazing of the 1st-floor façade has started.
  • Elevator assembly work has commenced.
  • Installation of metal structures on the 6th floor has been completed.
  • Installation of metal structures for the equipment platform (étagère) is in progress.
  • Preparatory work is underway for the procurement of equipment for the pumping stations and the heating unit.
  • Masonry work on internal partition walls is ongoing.
  • Installation of the 5th floor façade glazing systems has commenced, along with preparatory work for glazing installation.
  • Preparatory work for elevator installation is nearing completion.
  • Installation of metal structures on the 6th floor is nearing completion.
  • Installation of metal structures for the equipment platform (étagère) has started.
  1. Work continues on the laying of internal partitions.
  2. Installation of stained glass structures of the facade of the third floor.
  3. Preparatory work for the installation of elevators has begun.
  1. The installation of the metal structures of the technical floor has been completed.
  2. Work has begun on the installation of stained glass facade structures.
  1. Work is underway on the installation of metal structures of the technical floor.
  2. The monolithic work of all floors has been completed.
  1. The installation of the metal structures of the main building frame has been completed
  2. Monolithic work is underway to cover the 5th floor