Satpayev St. 29gThe facility has been commissioned
1. Handover works for the ventilated facade are in progress.
2. Handover works for the terrace waterproofing are in progress.
3. Piping layout works inside the building are nearing completion.
4. Installation works of ventilation ducts are ongoing.
1. Installation works for the entrance group have been completed.
2. Handover works for the ventilated facade are in progress.
3. Handover works for the terrace waterproofing are in progress.
4. Internal pipeline installation works are nearing completion.
5. Installation works for ventilation ducts are ongoing.
1. Installation of the entrance group is nearing completion.
2. Handover works for the ventilated façade are in progress.
3. Installation of internal piping within the building is nearing completion.
4. Installation of ventilation ducts has begun.
1. Installation works for the entrance group are nearing completion.
2. Installation of the ventilated facade and parapet cladding works are ongoing.
3. Pipeline installation works inside the building are in progress.
4. Ground preparation works for site landscaping are ongoing.
1. Roofing works on the 6th floor have been completed.
2. Installation of the entrance group is ongoing.
3. Installation of the ventilated façade and parapet cladding is ongoing.
4. Internal pipeline routing works are in progress.
5. Preparatory works for ground planning for site landscaping have been started.
1. Roofing works on the 6th floor have been completed.
2. Installation of the entrance group is in progress.
3. Installation of the ventilated façade and parapet cladding works are ongoing.
4. Installation and routing of pipelines inside the building are in progress.
1. Roofing works on the 6th floor are nearing completion.
2. Preparatory works for the installation of the entrance group are underway.
3. Installation of the ventilated façade and parapet cladding works are ongoing.
4. Internal pipeline distribution works are in progress.
1. Elevator commissioning works have been completed.
2. Roofing works on the 6th floor are in progress.
3. Installation of the ventilated facade is ongoing.
4. Internal pipeline installation works inside the building are ongoing.
1. Elevator commissioning works are ongoing.
2. Construction works for the terrace on the 5th floor have been completed.
3. Roofing works on the 6th floor are in progress.
4. Assembly of the 0.4 kV switchgear with connection to the transformer substation is ongoing.
5. Installation works of the ventilated façade are ongoing.
6. Monolithic works on the retaining wall on the eastern side have been completed.
7. Installation of internal pipeline systems within the building is ongoing.
1. Elevator commissioning works have been initiated.
2. Works on the construction of the 5th-floor terrace are in progress.
3. Roofing works on the 6th floor have been initiated.
4. Assembly of the 0.4 kV switchgear with connection to the transformer substation is in progress.
5. Installation works of the ventilated façade are ongoing.
6. Monolithic works on the retaining wall on the eastern side have been initiated.
7. Internal pipeline installation works inside the building are ongoing.
1. Elevator assembly works are ongoing.
2. Construction works for the 5th-floor terrace are in progress.
3. TP and 0.4 kV switchgear: assembly of the 0.4 kV switchgear with connection to the TP is ongoing.
4. Installation of the ventilated façade is ongoing.
5. Works on the retaining wall on the western side have been completed.
6. Preparatory works for the retaining wall on the eastern side are in progress.
7. Ventilation equipment has been procured.
1. Works on the installation of fire compartments and stained-glass glazing are nearing completion.
2. Elevator assembly works are ongoing.
3. Construction works on the 5th-floor terrace are in progress.
4. Installation of equipment for the pumping stations and the BTP has been completed.
5. Transformer substation (TS) and 0.4 kV switchgear. Assembly of the 0.4 kV switchgear with connection to the TS is ongoing.
6. Installation works of the ventilated façade are ongoing.
7. Backfilling works near the southern retaining wall have been completed.
8. Preparatory works on the western retaining wall are in progress.
1. Works on installing fire barriers and glazing the curtain walls are underway.
2. Elevator assembly works are ongoing.
3. Terrace construction on the 5th floor is in progress.
4. Installation of equipment continues:
• Pump stations – domestic drinking water, fire-fighting, and APT. Installation of electrical cables to the main switchboard;
• Assembly of the BTP has been completed. Installation of electrical cables to the main switchboard;
• TP and RU-0.4 kW. Assembly of RU-0.4 kW with connection to the TP is ongoing.
5. Installation of the ventilated façade continues.
6. Backfilling works near the southern retaining wall are underway.
7. Construction of retaining walls continues.
1. Works on installing fire barriers and glazing the façade with stained-glass units are underway.
2. Elevator installation and assembly works are ongoing.
3. Construction of the terrace on the 5th floor is in progress.
4. Installation of equipment continues:
• Pump stations for domestic water supply, fire extinguishing and APS (Automatic Fire Suppression). Pumps have been installed, pipeline connection works are in progress;
• Assembly of the BTP (block transformer substation) has been completed;
• TP and 0.4 kW switchgear: transformers have been installed, raised floor installation is ongoing.
5. Installation of the ventilated façade is ongoing.
6. Landscaping works are in progress.
7. Construction of retaining walls continues.
1. Installation of fire barriers and glazing of stained-glass windows is in progress.
2. Elevator assembly works are ongoing.
3. Assembly of the fire-fighting water tank is being completed.
4. Roofing works on the 6th floor and terrace works on the 5th floor are in progress.
5. Preparatory works for equipment installation have started, including:
• pumping stations for domestic water supply, fire-fighting, and APT systems;
• BTP;
• TP and switchgear 0.4 kV.
6. Installation of the ventilated façade is ongoing.
7. Preparatory landscaping works have begun on the eastern side.